STARRETT 196A1Z BACK PLUNGER DIAL INDICATOR W/CASE.001' $9.99. $14.99 shipping. 1 bid Ending Thursday at 12:57PM PST 21h 48m. 0-2 Inch Dial Indicator Travel Dial Indicator.001 Grad Lathe Precision Tool. 170 LBS Magnetic Base Dial indicator Holder w/ Fine Adjustment Mech Arm. Casing Plunger Systems. Swab-Rite Tool Corp.’s (SRTC) Natural Lift System patented Automatic Casing Plunger – a revolutionary method of capturing downhole pressure to unload liquids in gas wells, with no lift cost. The plunger is designed to sit on bottom, waiting for fluid to build-up. The hydrostatic forces trigger the plunger to close. The plunger head is designed to work on all toilets, including low flush. The handle design features a flat surface that is perfect for plunging. After use, simply replace the plunger in the canister for neat and sanitary storage; a built-in drip tray in the canister bottom catches excess water and allows it.
Installation process in accordance with the requirements of NBN EN1536:1999
1. Positioning and drilling of the first section of the drill casing (recoverable steel casing as temporary support during the boring process)
Concoyle 4 Casing Plunger
2. While drilling, the drill casing – inside equipped with a drilling head fixed on a rod - is oscillated into the soil. (back and forth movement / twisting in place)
3. & 4. As the drilling process progresses, soil is removed from the borehole by the excavating tool (« bucket barrel » excavating the pile shaft) and additional sections of casing are jointed (added) to protect the soil from collapsing into the borehole during drilling. When drilling in non-cohesive soils below the groundwater level, a water overpressure (delta h) should be created in the temporary casing.
Concoyle 4 Casing Plunger Tool
5. After reaching the design depth, clean-up of the borehole front, removal drilling tool, drilling fluid (water) pumped out from the bore.
Formation of the pile : insertion and lowering of the reinforcement cage, pouring of the concrete. In the presence of water, concreting is carried out by means of a plunger tube to avoid segregation of the concrete (tremie pipe technique).
Formation of the pile : insertion and lowering of the reinforcement cage, pouring of the concrete. In the presence of water, concreting is carried out by means of a plunger tube to avoid segregation of the concrete (tremie pipe technique).
6. During the continuous concreting process, the temporary casing elements are progressively withdrawn whereby the concrete forms the pile shaft.